What a good statement of work holds
27 November 2026 · 2 min read
The nine parts of a statement of work that keep a software project on track, and the points where the client approves.
A statement of work is the one document both sides sign before any work starts. A good one is short enough to read in a sitting and specific enough that nobody argues later about what was agreed. These are the nine parts we put in every one.
1. Scope
What is in, and what is out. The "out" list matters as much as the "in" list: it is where most disagreements start. If a payment provider, a second language or an admin screen is not in this project, the statement of work says so.
2. Deliverables
Each deliverable is named, with its owner. "A web app" is not a deliverable. "The candidate application flow, from the job advert to a submitted application, on phone and desktop" is.
3. Milestones
Dates, and what you approve at each. A milestone is a moment when working software is shown, tested and accepted, not a date on which a report is due.
4. Acceptance
How both sides know a deliverable is done. Usually a short list of checks: the flows that must work, the devices it must work on, the tests that must pass and who signs it off.
5. Team and roles
Who works on it and for how much of their time. A team of a tech lead, two developers and a tester at full time is a different promise from the same names at half time.
6. Ways of working
The tools, the meetings, the reporting and the contacts. For us that usually means a daily stand-up in your hours, a demo at the end of every two-week sprint, a written report every month, and work done in your own tools: Jira or Linear, GitHub or GitLab, Slack or Teams.
7. Changes
How a change of scope is asked for and agreed. Change is normal. What matters is that it is written down, priced and approved before the team starts on it, so the original plan stays honest.
8. Commercial terms
The price, the payment plan and the term. A project can be priced by outcome (a fixed price for the deliverables) or by month (a team at a monthly rate). The statement of work says which, and what happens at the end of the term.
9. Ownership
Code, designs and documents belong to the client. The work happens in the client's repositories and cloud, so nothing lives where the client cannot see it, and the handover at the end is a formality rather than a migration.
Where you approve
Three moments in an engagement need a yes from you: the agreed statement of work, each milestone, and any change of scope. Everything else runs on the rhythm the document sets out.
If you have a project in mind, send us a short brief: the work, the skills and the timing. We come back with a team shape and a draft statement of work, usually within a week.